By Paul Homewood
h/t Joe Public
This is an absolute disaster for Miliband’s floating windfarm target:
https://x.com/adissentient/status/1840690466477535685, which generated
.
Kincardine produced 144 GWh last year, so the total cost equates to £562/MWh.
They have a PPA in place which generated £13.3m at £92/MWh. On top of that ROC subsidies worked out at £217/MWh
Click this link for the original source of this article.
Author: Paul Homewood
This content is courtesy of, and owned and copyrighted by, https://notalotofpeopleknowthat.wordpress.com and its author. This content is made available by use of the public RSS feed offered by the host site and is used for educational purposes only. If you are the author or represent the host site and would like this content removed now and in the future, please contact USSANews.com using the email address in the Contact page found in the website menu.